Status construction  RV Anna Weber-van Bosse at Astilleros Armon in August 2025. Photo: NIOZ

The schip's cranes, frames and the CTD door are being installed, and the aft deck is made ready for exciting new science. Blasting and painting work is taking place on the outer decks.  With the scaffolding around the main mast beging removed,  the highest point of the ship is now in full view.

  • slide

    Port side and front

  • slide

    Sormec frame

  • slide

    Supports for solar panels

  • slide

    Traction winch

  • slide

    Main mast with equipment

  • slide

    MOB boat with crane

  • slide

    Overview from behind 

  • slide

    CTD hull door has been placed

  • slide

    Port side from behind

Recent pictures of the outside with all equipment being installed.

Inside the ship,the carpentry work of the accommodations is almost finished, and technical areas are being insulated and equipment installed in the state-of-the-art laboratories. The electrical systems and battery packs are being installed and tested step by step.

  • slide

    Crew cabin on the E deck

  • slide

    Lounge and meeting room

  • slide

    Cooling and freezing space for the galley

  • slide

    Engine room 

  • slide

    Alarm systems energised

  • slide

    Installation lift to the wheelhouse

  • slide
  • slide

    Switchboard room

  • Frames waiting for the battery packs

    Frames waiting for the battery packs

Recent pictures of the interior spaces, both for accommodation and for equipment and various systems

The site team in Vigo has to work hard to keep up with the progress being made and has been expanded with our own chief engineer and soon our captains will be joining. The coming months will be exciting, involving a lot of consultation, inspection and testing.